May 2025
The construction team has been hard at work, and we’re seeing great progress on all levels of the building. On the exterior, sidewalk pouring continues around the building, and construction has officially begun on the connector link that will connect Cedar Heights to our existing building. Inside, the fourth floor is coming together nicely, with apartment painting well underway and flooring and kitchen installations in progress—it’s starting to feel like home up there. On the third floor, trim is being installed throughout the apartments, while the second floor is nearly done with drywall hanging, with just a few units left to complete. Meanwhile, the first floor is seeing continued work in the living room and multipurpose area, including the framing of soffits and ongoing mechanical installations.
April 2025

February 2024
January 2024
During the month of January, windows and door installation was completed, the stone, siding and brick on the exterior of the building started. Plumbing teams continued to work on sanitary piping. HVAC and electricians continued to work on the rough-in work.





December 2024
December was a very busy month as the construction teams completed the framing of the 4th floor, set the trusses for the roof, installed shingles on the roof, and installed windows. While all of these things were happening on the outside of the building, electricians, plumbers, and HVAC workers started working inside to get rough in work done. The crane was also taken down and a base coat of asphalt was paved in the parking lot.



November 2024
During the month of November, framing of the 2nd and 3rd floors was completed, stairs were installed in the stair towers, a concrete curb was poured, and additional storm water piping was installed.




October 2024
In October, significant progress was made on the construction of the Cedar Heights Building, culminating in the completion of the last elevator and the underground plumbing, alongside the finalization of the building footers. The team successfully completed the last underground filtration bed, including the necessary piping for downspouts. Additionally, stone was laid to prepare the building pad for concrete, which was then poured, establishing a solid foundation. On the first floor, showers were brought on site and placed in the area of their respective apartments, and framing for the majority of the first floor was completed, marking a productive month for the project.





September 2024
During the month of September, building footings were installed, as well as the stair towers and elevator shafts. Plumbing and electrical teams also worked on underground plumbing and electrical.



July/August 2024
During the months of July and August, groundwork was completed.


June 2024
During the month of June, construction teams were busy removing three houses and a maintenance garage to make room for the Cedar Heights building.
May 2024
In May 2024 we held our groundbreaking ceremony for Cedar Heights!